Repair ZIL-5301

When removing the gearbox, it is necessary to unscrew the bolts securing the cabin floor cover, remove it and unscrew the flange for fastening the cardan shaft

Before checking the installation of the front wheels, check and, if necessary, adjust the axial clearances in the hub bearings and bring the tire pressure to normal

Requirements for parts and assemblies of the D-245 diesel engine
The cylinder block is the main body part of the diesel engine and is a rigid cast iron casting.
Four removable liners made of special cast iron are installed in the vertical bores of the block.

Removal and disassembly of the ZIL-5301 diesel engine
To dismantle the power unit, it is recommended to install the bus on an inspection pit, above which there is a lifting device

To ensure normal operation of the diesel engine, observe the following requirements for servicing the lubrication system:
- - fill the oil sump with only the oil recommended by the manufacturer.